+ Coloplast Coloplast

Project Value: £9 million

Project Size - 135,000sqft


New bespoke facility for medical technology company Coloplast UK by Roxhill Developments. Having been based in Peterborough since opening its UK headquarters in the city in 1978, the new building ensures Coloplast UK is able to service all of its customers directly from the UK, allowing the company to keep more product lines in stock, improve capacity to fulfil orders on the same day and reduce lead times on orders.


The scope covered the main building construction phase together with the fit out design of the office and welfare facilities.


Coloplast

+ DSV - Peterborough - hide

DSV - Peterborough

DSV - Peterborough

Project Value: £15 million

Project Size - 300,000sqft


Storage and distribution warehouse facility for DSV UK Ltd offering a clear internal height of 15m. Unit was designed to meet institutional standards with a service yard to the west elevation sized to provide lorry parking to accommodate 101 trailer spaces.


In addition the unit is served by an integral 2-storey office and welfare block, 2-storey pod office block and open fronted canopy to the level entry doors as well as 223 parking spaces.



+ Kingsley Beverages Kingsley Beverages

Project Value: £12 million

Project Size - 145,000sqft


This as a purpose-built manufacturing, bottling and distribution facility at Peterborough Gateway for Kingsley Beverages. The building has a clear internal height of 12.5m and is provided with.7no. dock levellers and 4no. level access doors. The unit has a PET line production capacity for 20,400 bottles per hour and a canning line with capacity of 36,000 cans per hour which allow distribution through the UK as well as export to Kingsley operations across the globe.


The scope covered the main building construction as well as £6million of base build enhancements/ fit-out works related to the soft drinks production. This included the transformation of the warehouse area to incorporate production facilities, flavour rooms, effluent tanks and 120 tonne sugar silos, alongside a 4,500sqft extension to the office area which houses additional staff welfare accommodation. Key challenges of the project included the specialist drainage required due to the production processing involved and the strict ATEX requirements due to the fine powders utilised. Other specialist services included sprinklers, compressors, CO2 distribution and specialist water treatment.


Kingsley Beverages

+ E-leather – Peterborough - hide

E-leather – Peterborough

E-leather – Peterborough

Project Value: £11 million

Project Size - 230,000sqft


A new production facility for E-leather, who manufacture high-technology composition leather for rail and aviation companies. The project consisted of a large production space with 12.5m clear internal height and a 3-storey HQ office area.